Tentative Bowie Construction Schedule
Below is the progress report and tentative construction schedule for the new Bowie Elementary School:
Completed
Site Drawings
Final Pricing
Site Layout
Grade for New Drive and Portables
Rough Grade Site
Sleeves under New Drive
In Progress
Fire Line (7/2)*
Move-in and Level Portables (7/14)
Sanitary Sewer (7/16)
Gas Line (7/16)
Concrete Drive (7/21)
Sidewalks (7/28)
Water Line (7/30)
Phone/Data System (8/7)
Temporary Irrigation (8/7)
Install Decks and Sidewalks (8/11)
Final Clean (8/13)
*Dates in parenthesis signify the projected completion date for each project.